Project Duration
Stipulated Date of Commencement
April 24 2018
Stipulated Date of Completion /
Likely Date of Completion February 23 2019
Likely Date of Completion February 23 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 23,654,992.00
Awarded for
₹ 24,828,170.99
Project highlights
Repairs/Upgradation of School
Contractors
M/s. H. Candolkar & Sons
Consultants
M/s. Creative Abode.
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-BicholimTaluka-Package E (G.P.M.S. Nanoda, G.P.M.S. Advalpal, G.P.S. Amthane)
View Project
Repairs/Upgradation & Maintenance of Government Schools In the State of Goa- Sattari Taluka: Package-G (GHS Surla, GPS Surla, GPS Gholwada, GHS Keri)
View Project
Reconstruction of school at GPS Bicholim (Central)- Erection of 200KVA DTC along with the associated H.T UG Cable
View Project