Project Duration
Stipulated Date of Commencement
June 19 2021
Stipulated Date of Completion /
Likely Date of Completion August 31 2023
Likely Date of Completion August 31 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ . 1,25,98,760 .00
Awarded for
₹ 13,049,686.60
Project highlights
Construction of Government Primary School at Savai , Ponda Goa
Designed with modern architectural looks.
Proposed building consists of Ground + 1 RCC framed structure.
The proposed building meant for houses a Government Primary School consisting of four classrooms for standards 1 to 4 in addition to an Anganwadi.
The building will have Vitrified flooring and Galvalume sheets sloping roof.
Provision for Library, Smart Classroom, Music Room & Sports Room on Ground Floor along with toilet block.
Provision for a Multipurpose hall with a seating of capacity 200 people on the first along with toilet block.
Total built up area of the building is 465.00 sqm.
Provision of shot blasted pavers along the periphery of the building