Project Duration
Stipulated Date of Commencement
February 20 2014
Stipulated Date of Completion /
Likely Date of Completion August 29 2014
Likely Date of Completion August 29 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,668,077.00
Awarded for
₹ 7,177,614.00
Project highlights
Reconstruction of Primary School with G+1 Structure.
Contractors
M/s. Trivikram Constructions
Consultants
M/s. Bhaskar Wagle and Associates