Project Duration
Stipulated Date of Commencement
February 12 2019
Stipulated Date of Completion /
Likely Date of Completion July 21 2019
Likely Date of Completion July 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,854,293.99
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates
See Similar Projects
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa – Civil, Plumbing and Electrical works-Bicholim Taluka – Package H (G.P.S Kharekhajan- Virdi, G.P.S Kudchire, G.P.S. Pratap Nagar- Harvalem, G.H.S. Late Jayendra J. Rane- Kudchire)
View Project
Repairs/Upgradation & maintenance of Government Schools in State of Goa – Civil, Plumbing & Electrical works – Package D – Quepem Taluka (GPS Katta Fatorpa, GPS Shirlim)
View Project
Repairs & Upgradation of Government Schools in the State of Goa: GHS –Mangoor Hill
View Project