Project Duration
Stipulated Date of Commencement
February 12 2019
Stipulated Date of Completion /
Likely Date of Completion July 21 2019
Likely Date of Completion July 21 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 5,000,000.00
Awarded for
₹ 5,854,293.99
Project highlights
Repairs/Upgradation and Maintenance of Govt. schools in the state of Goa
Contractors
M/s. Sirajuddin Beig
Consultants
M/s. Vaishali Pednekar Associates