Project Duration
Stipulated Date of Commencement
December 17 2011
Stipulated Date of Completion /
Likely Date of Completion June 16 2012
Likely Date of Completion June 16 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 1,425,000.00
Awarded for
₹ 1,425,000.00
Contractors
M/s. Thyssenkrupp Elevators (I) Pvt. Ltd.
Consultants
M/s. Gurudutt Sanzgiri
See Similar Projects
Upgradation of Infrastructure in the Rural Areas under Deendayal Panchayat Raj Infrastructure Development (Golden Jubilee) Scheme, 2013 – Construction of Panchayat Ghar and Market Complex at VP Cotorem.
View Project
Dehumidification System.
View Project
Public Works in Sankhali Constituency
View Project





