Project Duration
Stipulated Date of Commencement
December 09 2019
Stipulated Date of Completion /
Likely Date of Completion March 08 2021
Likely Date of Completion March 08 2021
Status
100%
Completed
Cost (₹)
Estimated at
₹ 19,496,224.50
Awarded for
₹ 20,444,375.59
Contractors
M/s. A. Y. Gulumkar
Consultants
M/s. Creative Abode