Project Duration
Stipulated Date of Commencement
August 26 2016
Stipulated Date of Completion /
Likely Date of Completion November 25 2017
Likely Date of Completion November 25 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,051,673.00
Awarded for
₹ 14,133,458.98
Project highlights
(1) Ground floor consists of 1 nos. of shop of size 2.35 x 4.54.mt
(2) First floor consists of Panchayat Office, seperate Talathis Office, Sarpanch , Secretary and Conference room, Animal Husbandary & Electricity Dept and seperate toilets.
Contractors
M/s.Vaishnavi Infrastructure
Consultants
M/s. Creative Abode
See Similar Projects
Construction of Library Building at Margao.
View Project
Construction of Shri. Manohar Parrikars Smriti Sthal at Miramar
View Project
Supply, Installation, Testing and Commissioning of 120 KVA UPS.
View Project