Project Duration
Stipulated Date of Commencement January 19 2019
Stipulated Date of Completion /
Likely Date of Completion
April 18 2020
Status
100%
Completed
Cost (₹)
Estimated at ₹ 15,317,222.00
Awarded for ₹ 17,058,453.10

Project highlights

(1) Ground Floor
(a) It accomodates nine numbers of shops.
(b) Ladies and Gents Toilet.
(II) First Floor
(a) It consists of Administration Office, Secretary Cabin, Sarpanch Cabin, Conference Room,Gram Sevak Office, Talathi Office, Pantry, Library.
(b) Ladies & Gents Toilet.
(III) Second Floor
(a) Multipurpose Hall to cater to 150 people with an area of 175 sq.m.
(b) Ladies & Gents Toilet.

 
Gallery Image
Contractors
M/s. Mahabaleshwar M. Naik & Co.
Gallery Image
Consultants
M/s. S.H. Patil
 
Similar Projects

See Similar Projects

Similar Project

Phase I : Land Development.

View Project
Similar Project

Development of service road and site development at Mont Boa Vista for Exposition 2014.

View Project
Similar Project

Air conditioning

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.