Project Duration
Stipulated Date of Commencement
July 03 2015
Stipulated Date of Completion /
Likely Date of Completion April 02 2016
Likely Date of Completion April 02 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,759,455.25
Awarded for
₹ 36,700,220.20
Project highlights
Construction of new building for Panchayat Ghar
Contractors
M/s. Trivikram Constructions
Consultants
M/s. Oracle Structural Consultants