Project Duration
Stipulated Date of Commencement
November 19 2021
Stipulated Date of Completion /
Likely Date of Completion February 18 2023
Likely Date of Completion February 18 2023
Status
100%
Completed
Cost (₹)
Estimated at
₹ 28,288,129.00
Awarded for
₹ 30,058,361.00
Project highlights
The Panchayat Ghar is a G+ 2 structure having Bank, Library, shops, Fish Market, Village Panchayat Office, Hall for Gram Sabha, Multipurpose Hall, etc.
Contractors
M/s.Indage Development Construction Pvt. Ltd
Consultants
M/s. Vijaykumar Sawant Associates