Project Duration
Stipulated Date of Commencement March 27 2007
Stipulated Date of Completion /
Likely Date of Completion
March 26 2008
Status
100%
Completed
Cost (₹)
Estimated at ₹ 54,371,959.00
Awarded for ₹ 69,139,000.00
 
Gallery Image
Contractors
M/s. IVRCL Infrastructure & Projects Ltd.
Gallery Image
Consultants
M/s. Datta Kare Associates
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Construction of Swimming pool at Ponda Sports Complex – Additional works such as Jogging Track, Road, Compound wall, Security Cabin etc.

100% completed
 
Project Duration
Stipulated Date of Commencement February 12 2009
Stipulated Date of Completion /
Likely Date of Completion
May 11 2009
Status
100%
Completed
Cost (₹)
Estimated at ₹ 50,71,379.00
Awarded for ₹ 47,00,750.52
 
Contractors
Contractors
M/s. Rohit Equipments
Consultants
Consultants
M/s. Datta Kare Associates
Similar Projects

See Similar Projects

Similar Project

Upgradation/Renovation of Government College at Quepem, Goa -Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.

View Project
Similar Project

Repairs/Upgradation & Maintenance of Govt. Schools in the State of Goa – (Ponda Taluka) – (GPS Dharzo,GPS Gaune No 2 , GPS Gauthan Priol, GPS Hanso & GPS Parampai )

View Project
Similar Project

Supply & Installation of Furniture for Government Schools and Colleges in the State of Goa

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.