Project Duration
Stipulated Date of Commencement
December 12 2016
Stipulated Date of Completion /
Likely Date of Completion January 25 2017
Likely Date of Completion January 25 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 14,039,447.00
Awarded for
₹ 12,710,482.00
Project highlights
The scope of work includes:
a) Supply, installation, testing & commissioning of 86 Watts, LED outdoor street lights along with 9 mtrs height hot dip galvanized PU painted conical poles with single arm brackets-109 nos.
b) Supply of 40 Watts, LED outdoor street lights along with 6 mtrs height hot dip galvanized PU painted conical poles with single arm brackets-13 nos.
Contractors
M/s. James Electrical
Consultants
In-house
(GSIDC)
See Similar Projects
Construction of Bridge across Baga creek at Baga including approaches.
View Project
Sanvordem Bridge
View Project
Providing and applying high build, crack building, electromeric, protective and waterproof coating to the Grade separator (2 flyovers) at Dabolim airport.
View Project