Project Duration
Stipulated Date of Commencement
November 21 2014
Stipulated Date of Completion /
Likely Date of Completion February 21 2015
Likely Date of Completion February 21 2015
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,325,978.00
Awarded for
₹ 54,600,581.10
Project highlights
Conversion of electrical overhead lines to underground cables.
Contractors
M/s. Goa Friends Engineering & Electricals Pvt. Ltd.
Consultants
M/s. Nitin Arolkar