Project Duration
Stipulated Date of Commencement
December 27 2016
Stipulated Date of Completion /
Likely Date of Completion October 26 2017
Likely Date of Completion October 26 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 20,288,705.00
Awarded for
₹ 22,229,070.00
Project highlights
Construction of box culvert across st. Inez creek with foothpath and approach road both side.
Contractors
M/s. Expanse India Buildcon Pvt. ltd.
Consultants
M/s. LKS India Pvt. Ltd.
See Similar Projects
Construction of bridge between Tharmas to Ozari Sangaowada in Dhargal Constituency.
View Project
Phase I : Land Development.
View Project
Construction of Concrete Pavement Road and other development work from Miramar Circle to NIO Circle and Raj Bhavan
View Project





