Project Duration
Stipulated Date of Commencement
April 23 2016
Stipulated Date of Completion /
Likely Date of Completion October 28 2017
Likely Date of Completion October 28 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 236,470,437.00
Awarded for
₹ 242,441,097.11
Project highlights
Cfonstruction of 2 Lane Bridge with approaches.
Contractors
M/s. Larsen & Toubro Ltd.
Consultants
M/s. Rahul Deshpande
Sub Works
This project involved 2 sub works. The details of the same available below
1
Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 11 KV Cable
100% completed
Project Duration
Stipulated Date of Commencement
November 29 2017
Stipulated Date of Completion /
Likely Date of Completion December 05 2017
Likely Date of Completion December 05 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 253,495.00
Awarded for
₹ 276,450.00
Project highlights
The scope of work includes supply, installation, testing & commissioning of 11 KV, 3C x 300 sq. mm, underground armored cable – 120 meters length.
Contractors
M/s. Pristine Engineering Services
Consultants
M/s. Rahul Deshpande
2
Construction of Bridge across Rua de Ourem Creek, Panaji – Shifting of 33 kV Overhead Lines
100% completed
Project Duration
Stipulated Date of Commencement
January 17 2018
Stipulated Date of Completion /
Likely Date of Completion January 21 2018
Likely Date of Completion January 21 2018
Status
100%
Completed
Cost (₹)
Estimated at
₹ 571,048.00
Awarded for
₹ 597,920.00
Project highlights
The scope of work includes dismantling of existing 33kV overhead lines and installation, testing & commissioning of 33 KV, 3C x 400 sq. mm, underground armored cable supplied by Goa Electricity Department.
Contractors
M/s. Pristine Engineering Services
Consultants
M/s. Rahul Deshpande
See Similar Projects
Hot mixing and Improvement of Internal Roads in V. P. Dramapur, Sirlim in Velim Constituency.
View Project
Hot mixing & Improvement of Road from Betul Bridge to Baradi Junction in Velim Constituency.
View Project
Design and Construction of bridge over river Kushawati at Adem, Sanguem Taluka.
View Project