Project Duration
Stipulated Date of Commencement
May 01 2008
Stipulated Date of Completion /
Likely Date of Completion January 31 2009
Likely Date of Completion January 31 2009
Status
100%
Completed
Cost (₹)
Estimated at
₹ 25,895,502.00
Awarded for
₹ 38,898,833.00
Project highlights
* Length of the bridge is 62 m.
* Carriageway of the bridge is 7.5 m with 1 m footpath on one side.
*Superstructure consists of RCC deck.
* Bridge comprises of 7 piers and 2 abutments.
* Length of approach roads is 93.50 m in the North and 63.00 m in the South with adequate lighting and proper drainage system.
Contractors
M/s. Aditya Construction Company
Consultants
M/s. Keni & D’Souza
See Similar Projects
Maintenance of bridges constructed by GSIDC for a period of five years (North Goa) :-Civil works.
View Project
Construction of Pedestrian pathway on existing approach to road over bridge at Rawanfond Margao Goa
View Project
Improvement and Upgradation of road network from MDLB Hospital to Baina Sea Shore, Shafi Masjid to Baina Recreational Club, Bharat lines to Headland Sada Junction in Mormugao Constituency.
View Project