Project Duration
Stipulated Date of Commencement
February 26 2004
Stipulated Date of Completion /
Likely Date of Completion August 25 2004
Likely Date of Completion August 25 2004
Status
100%
Completed
Cost (₹)
Estimated at
₹ 11,611,394.00
Awarded for
₹ 14,350,277.00
Project highlights
• First four lane bridge in Goa.
• The bridge serves as an important link joining the southern part of Goa to the Margao city.
• Length : 18.6 m, width : 19 m including footpaths.
• Length of approaches : 100 m, width : 19 m with adequate lighting and proper drainage system.
Contractors
M/s. Laxmi Civil Engg. Services Pvt. Ltd.
Consultants
M/s. Keni & D’Souza
See Similar Projects
Construction of vehicular bridge at Hedode including approaches in Sattari, Goa.
View Project
Construction of Training Wall & upgradation of fishing jetty at Cutbona (South Goa). (Revised Scope of work) Construction of fishing jetty at Cutbona (South Goa).
View Project
Laying of paver blocks on Promenade/ Footpath along D. B. Marg in Panaji.
View Project