Project Duration
Stipulated Date of Commencement
February 07 2005
Stipulated Date of Completion /
Likely Date of Completion May 06 2005
Likely Date of Completion May 06 2005
Status
100%
Completed
Cost (₹)
Estimated at
₹ 4,495,956.00
Awarded for
₹ 5,905,000.00
Project highlights
• Length : 16 m.
• The bridge is cast-in-situ inverted L-beam superstructure.
• Carriageway 4.5 m wide.
• Approaches on Nuem side.
Contractors
M/s. Sunil Constructions j/v M/s. Descon
Consultants
M/s. Madhav Kamat & Associates