Project Duration
Stipulated Date of Commencement March 03 2007
Stipulated Date of Completion /
Likely Date of Completion
September 02 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 43,533,748.34
Awarded for ₹ 51,954,331.00

Project highlights

• Total built-up area of 2,400 sq.m.
• Vegetable vendors 100 nos.
• Fruit vendors 25 nos.
• Fish vendors.
• Public Service Café.
• Shops.
• Gallery overlooking the river.
• Provision for chiller room.
• Public toilets.
• Inspection office.
• Security cabin.
• Loading & unloading platform.
• Provision of road to connect to KTC bus stand.
• Sufficient parking for visitors and service vehicles.
• Feasibility of 2000 people to do transactions in the market at a time.
• Road and parking zones shall be asphalted.
• Adequate entry and exit points.

 
Gallery Image
Contractors
M/s. Ruby Realtors Pvt. Ltd.
Gallery Image
Consultants
M/s. Nabar Paraz Associates
 
Similar Projects

See Similar Projects

Similar Project

Supply, Installation, Testing and Commissioning of Library Software for District Library at Navelim, Margao

View Project
Similar Project

Demolition and reconstruction of Market Complex at Bhoma Adcolna Panchayat Banastarim Goa -Civil, Plumbing, Electrical, HVAC, Lifts and Fire Fighting works

View Project
Similar Project

Dehumidification System

View Project
x
  • 150yrs of Celebrating Mahatma Gandhi
  • Digital India
  • Government Of Goa
  • Incredible India
  • NationalPortal India gov
Disclaimer: Translated by Directorate of Official Language, Government of Goa. Note: In any case for legal interpretation, English version will prevail.