Project Duration
Stipulated Date of Commencement
January 14 2013
Stipulated Date of Completion /
Likely Date of Completion May 13 2013
Likely Date of Completion May 13 2013
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,848,415.93
Awarded for
₹ 4,426,921.55
Project highlights
External Electrical Work
Contractors
M/s. Ohm Engineers & Electricals Pvt. Ltd.
Consultants
M/s. Rahul Deshpande & Associates