Project Duration
Stipulated Date of Commencement
May 06 2012
Stipulated Date of Completion /
Likely Date of Completion November 05 2012
Likely Date of Completion November 05 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 7,551,260.00
Awarded for
₹ 7,326,587.00
Project highlights
Acoustic works for Multipurpose hall
Contractors
M/s. R. S. Lawande
Consultants
M/s. Rahul Deshpande & Associates