7. |
Present Status |
: |
1) At first floor level, works like roofing, flooring, plastering, false ceiling & POP completed in heritage part while flooring & plastering in progress in Annexe building. 2) At ground floor level, 80% of flooring completed, plaster & POP completed. 3) Toilet dado in progress. 4) Painting / polishing - Work in progress 5) External paint final coat to be taken up after completion of footpath work. (6) Strengthening of roof truss in Annexe building completed and columns removed. (7) Internal electrical wiring work in progress. Plumbing work in progress. Construction of drain work in progress. Flooring in courtyard in progress. Work of PU coating for wooden flooring in progress. External sewerage line completed. Room in annexe building where electrical material was stored is handed over to contractor. |