7. |
Present Status |
: |
* The contractor has been directed to remobilize men & machinery at site vide our letter dated 03/03/2010. * The consultant has been requested to mobilize their team for carrying out consultancy services vide our letter dated 05/03/2010. * Meeting was held on 08/03/2010 and 09/03/2010 along with the Chairperson, Sanquelim Municipal Council, Municipal Engineer I, Municipal Engineer III, Police Inspector Sanquelim, R.T.O., Bicholim, A. E., PWD, consultant and contractor to check out the future course of action in view of laying the sewer lines. The contractor was asked to give the schedule / progress of executing the work keeping in mind that any excavated portion should be backfilled by 15/05/2010 as per the statutory requirements. Drain work at Harvalem is in progress. |