7. |
Present Status |
: |
External plaster, aluminium grill work and roofing completed. Flooring completed on 2nd, 3rd, 4th, 5th, 6th floor. Staircases, flooring completed. External vehicular ramp is in progress. Sample of passage flooring approved by Client Department and MD. The contractor has starting flooring. Masonry for graphic studio on ground floor completed. Polishing of kotah flooring in progress in basement area, ground floor hall and adm. Second floor non-AC area polishing completed. Polishing started on 4th floor in non-AC area. |