1. |
Name of Project |
: |
Development of infrastructure for Panaji Minor Port : Construction of Jetty at Brittona |
|
2. |
Project Management Consultant |
: |
M/s. Construma Consultancy Pvt. Ltd. |
|
3. |
Contractor |
: |
M/s. Kirloskar Constructions & Engineers Limited |
|
4. |
Awarded Cost |
: |
Rs. 34,552,373.00 |
|
5. |
Stipulated Date of Commencement |
: |
26/04/2007 |
|
6. |
Physical Progress |
: |
99% |
|
7. |
Present Status |
: |
The testing of FF & transformer can be completed on restoration of HT connection. File forwarded to Electricity Department and RIO on 09/08/2010 for restoration of HT supply and approval of electrical works. Inspection by RIO held on 18/08/2010 & Electricity Department (MRT) on 31/08/2010. Electricity Department has requested for certain changes, compliance by contractor. |