7. |
Present Status |
: |
Work Order is issued to M/s. Shilpi Constructions Pvt. Ltd., on 24th June 2010. Excavation work, PCC, base waterproofing, reinforcement tying and concreting of base, side walls for underground tank completed. Steel reinforcement for walls of U.G. tank top slab is in progress. Plumbing work for geysers in toilet block is completed. External panel room excavation is in progress. Filming for door ventilators is in progress. Head board fixing for existing beds is in progress. Fabrication work for dias in Multipurpose Hall is in progress. |