Present Status |
: |
Work order issued to the contractor, M/s. Ultracon Constructions Pvt. Ltd. on 27/04/2010. Wooden piling 94 m complete out of 94 m. PCC + plumb concrete - 300 m complete out of 400 m. Retaining wall - 220 m complete out of 400 m. Work stopped due to rains / flooding of the working area due to rise in water level in the lake. |