| Construction of bridge between Tharmas to Ozari Sangaowada in Dhargal Constituency
|
|
|
|
1. |
Name of Project |
: |
Construction of bridge between Tharmas to Ozari Sangaowada in Dhargal Constituency |
|
2. |
Project Management Consultant |
: |
M/s. Mahimtura Consultants Pvt. Ltd. |
|
3. |
Contractor |
: |
M/s. Aditya Construction Co. |
|
4. |
Awarded Cost |
: |
Rs. 18,59,11,708/- |
|
5. |
Stipulated Date of Commencement |
: |
28/04/2010 |
|
6. |
Physical Progress |
: |
5% |
|
7. |
Present Status |
: |
Land acquisition process is in progress. Work order issued to M/s. Aditya Construction Co. on 13/04/2010. Soil exploration completed, contractor has commenced with piling on 18/08/2010. | |
| |
|
 |
|