| Re-construction / upgradation of Primary Health Centre at Sanquelim, Goa - Fire fighting and PA system
|
|
|
|
1. |
Name of Project |
: |
Re-construction / upgradation of Primary Health Centre at Sanquelim, Goa - Fire fighting and PA system
|
|
2. |
Project Management Consultant |
: |
M/s. Consulting Engineering Services (India) Pvt. Ltd.
|
|
3. |
Contractor |
: |
M/s Japsin Jacob Wire Drawing Pvt. Ltd. |
|
4. |
Awarded Cost |
: |
Rs. 7,290,025.00
|
|
5. |
Stipulated Date of Commencement |
: |
11/3/2010
|
|
6. |
Physical Progress |
: |
35% |
|
7. |
Present Status |
: |
Materials such as GI pipes, cable etc., are approved. Agency delivered materials (part) at site on 03/06/2010 and hydrant pipe laying work is in progress. Fire alarm cabling work is in progress. | |
| |
|
 |
|