| Reconstruction / Upgradation of Primary Health Centre at Sanquelim, Goa – Internal Electrical works.
|
|
|
|
1. |
Name of Project |
: |
Reconstruction / Upgradation of Primary Health Centre at Sanquelim, Goa – Internal Electrical works. |
|
2. |
Project Management Consultant |
: |
M/s. Consulting Engineering Services (India) Pvt. Ltd.
|
|
3. |
Contractor |
: |
M/s. Mohan Electricals |
|
4. |
Awarded Cost |
: |
5,12,2,999/-
|
|
5. |
Stipulated Date of Commencement |
: |
26/06/2009
|
|
6. |
Physical Progress |
: |
62%
|
|
7. |
Present Status |
: |
Electrical material such as conduits, accessories wires are received at site. Conduiting work on all floors is almost complete. Wiring work on ground floor is complete and the same is in progress on other floors. LT panels inspected and delivered at site. | |
| |
|
 |
|