7. |
Present Status |
: |
RCC of main building - 95% completed. Laterite masonry, brick masonry, internal plastering, external plastering, roof waterproofing and plumbing works are in progress. Mock up of various samples such as flooring, external painting etc. was approved. Mortuary, substation and fire escape staircase works are in progress. Excavation for septic tank, deep burial pit is in progress. Dado work on ground floor / first floor and second floor is in progress. Shuttering of wall of UG tank is in progress, flooring of staircase is in progress. Kotah flooring of OTs masonry etc., is in progress.MoU is pending with Directorate of Health Services. |