Design & Construction of bridge at Cumbarjua on RCC bored pile foundations
1.
Name of Project
:
Design & Construction of bridge at Cumbarjua on RCC bored pile foundations.
2.
Project Management Consultant
:
M/s. STUP Consultants Pvt. Ltd. /
M/s. Mahimtura Consultants Pvt. Ltd.
3.
Contractor
:
M/s. Banka Constructions
4.
Awarded Cost
:
Rs. 14,24,99,999.00
5.
Stipulated Date of Commencement
:
06/03/2009
6.
Physical Progress
:
30%
7.
Present Status
:
30 nos. of piles out of 32 completed. Pile cap of pier P1 & P2 complete. Initial pile testing completed. Routine pile test completed on 04/06/2010. Piling work for abutment A1 stopped due to rains. Fabrication of staging for superstructure in progress.