1.

Name of Project

:

Design & Construction of bridge at Cumbarjua on RCC bored pile foundations.

2.

Project Management Consultant

:

M/s. STUP Consultants Pvt. Ltd. /

M/s. Mahimtura Consultants Pvt. Ltd.

3.

Contractor

:

M/s. Banka Constructions

4.

Awarded Cost

:

Rs. 14,24,99,999.00

5.

Stipulated Date of Commencement

:

06/03/2009

6.

Physical Progress

:

30%

7.

Present Status

:

30 nos. of piles out of 32 completed. Pile cap of pier P1 &  P2 complete. Initial pile testing completed. Routine pile test completed on 04/06/2010. Piling work for abutment A1 stopped due to rains. Fabrication of staging for superstructure in progress.

 
 
 