Present Status |
: |
Scope of work :Excavation for road widening, Rubble soling for road widening, Laying of pipe ducts, concreting of drain walls & Laying of water bound Macadam completed.a)Pipe ducts-930 m completed b) Drain walls-930m c)W.B.M(GRADE II)-970m (R.H.S), W.B.M(GRADE III)-800m, culvert slab complete. Electrical works in progress. Fixing of kerb stones, pavers in progress. |