Rawanfond Junction to ROB (Total length : 2010 m) : Concreting of drain walls including rubble soling and PCC laying of precast RCC slabs, fixing of kerb stones, fixing of pavers is complete. Corporation Bank to Church (Total length : 1810 m) : The above scope of work for major stretch of road is completed.
Cine Vishant to Corporation Bank (Total length : 1950 m) : The above scope of work for major stretch of road is completed. Chandrawada (Total length : 540 m) : The above scope of work is complete. Asphalting of road complete. Kerb painting balance.
Fatorda Circle to Colva Circle (Total length : 700 m) RHS:- Ch. 0.00 to Ch.550 – above scope of work is complete LHS: - Ch.0.00 to Ch.280 - completed upto fixing of kerb stone, fixing of pavers in progress. Cine Lata Paving works near Cine Lata were commenced. Kerb painting balance. |