Construction of Central Library Building at Patto, Panaji, Goa - False ceiling work

1.

Name of Project

:

Construction of Central Library Building at Patto, Panaji, Goa - False ceiling work.

2.

Project Management Consultant

:

M/s.Architecture Autonomous PMC with Frischmann Prabhu India (I) Pvt Ltd.

3.

Contractor

:

M/s. Damian de Goa

4.

Awarded Cost

:

Rs.1,29,68,300.00

5.

Stipulated Date of Commencement

:

28/02/2009

6.

Physical Progress

:

22%

7.

Present Status

:

Work order issued to Contractor on 13/02/2009. The Consultant has submitted working drawings on 26th March 2009 for working out quantities. Provisional extension granted to the Contractor upto 30/11/2010. Contractor has procured some materials  and work started  in non-AC areas. Framework at 2nd, 3rd, 4th, 5th floor in progress (90% done). Fixing of ceiling panels on hold pending HVAC work and fire fighting work. Floor completed on 2nd & 4th floor in non-AC area. On 3rd floor, work is on hold pending CCTV cabling.

 
 
 