| Construction of 400 bedded District hospital at Margao, Goa.
|
|
|
|
1. |
Name of Project |
: |
Construction of 400 bedded District hospital at Margao, Goa. |
|
2. |
Project Management Consultant |
: |
M/s Kirloskar Consultants Ltd. |
|
3. |
Contractor |
: |
M/s. M. Venkata Rao Infra Projects Pvt. Ltd. |
|
4. |
Awarded Cost |
: |
Rs. 926,631,978.97 |
|
5. |
Stipulated Date of Commencement |
: |
05/11/2008 |
|
6. |
Physical Progress |
: |
28% |
|
7. |
Present Status |
: |
Work order issued to the contractor on 21/10/2008. However, SGPDA issued NOC / approval on 26/02/2009. The Margao Municipal Council issued construction license on 10/03/2009. The basement (raft slab / pile caps / beams) 100% complete (OPD, casualty & CSSD area). Coba filling work in casualty and CSSD area in progress. Admin block raft / pile cap nearing completion. OPD area first slab complete. Casualty first slab shuttering in progress. Overal 95% basement work completed and first slab in casualty & second slab in OPD in progress. | |
| |
|
 |
|