Construction of 400 bedded District hospital at Margao, Goa.

1.

Name of Project

:

Construction of 400 bedded District hospital at Margao, Goa.

2.

Project Management Consultant

:

M/s Kirloskar Consultants Ltd.

3.

Contractor

:

M/s. M. Venkata Rao Infra Projects Pvt. Ltd.

4.

Awarded Cost

:

Rs. 926,631,978.97

5.

Stipulated Date of Commencement

:

05/11/2008

6.

Physical Progress

:

28%

7.

Present Status

:

Work order issued to the contractor on 21/10/2008. However, SGPDA issued NOC / approval on 26/02/2009. The Margao Municipal Council issued construction license on 10/03/2009. The basement (raft slab / pile caps / beams) 100% complete (OPD, casualty & CSSD area). Coba filling work in casualty and CSSD area in progress. Admin block raft / pile cap nearing completion. OPD area first slab complete. Casualty first slab shuttering in progress. Overal 95% basement work completed and first slab in casualty & second slab in OPD in progress.

 
 
 
TERMS & CONDITIONS
| | |
Designed by Goa Cyber Works
 

Copy Right 2006- Goa State Infrastructure Development Corporation Ltd.