1. |
Name of Project |
: |
Construction of bridge at Guleli - Padeli in Sattari Taluka, Goa. |
|
2. |
Project Management Consultant |
: |
M/s. Mahimtura Consultants Pvt. Ltd.
|
|
3. |
Contractor |
: |
M/s. Aditya Construction Co. |
|
4. |
Awarded Cost |
: |
Rs. 152368897.5 |
|
5. |
Stipulated Date of Commencement |
: |
10/01/2009
|
|
6. |
Physical Progress |
: |
70% |
|
7. |
Present Status |
: |
Four spans cast. Shuttering / centering work for balance one span is in progress. The work for approach road is in progress. |