HV Menu example
 
Construction of single lane bridge in village Dongrim, Village Panchayat Azzosim, Mandur

1.

Name of Project

:

Construction of single lane bridge in village Dongrim, Village Panchayat Azzosim, Mandur

 

2.

Project Management Consultant

:

M/s. Keni & D'Souza   

3.

Contractor

:

M/s.Ameya Kumar Constructions

4.

Awarded Cost

:

Rs. 94,657,774.80

5.

Stipulated Date of Commencement

:

19/06/2008

 

6.

Physical Progress

:

58%

7.

Present Status

:

Both abutments and both piers / pier caps  completed, land acquisition process initiated. TCP approval awaited for land acquisition process. Concreting of girder  & slab for span between P1 and abutment Neura done. Letters sent to soil expert for checking foundation design and soil stabilization. Two offers received out of three.

 
 
 