Present Status |
: |
1.Block A - False ceiling work, gypsum coves, window sills, granite cladding, tiling is in progress. Plumbing work and water proofing of toilets, corridors, roof are in progress 2.Block B - Centering and shuttering for dome has been started. 3.Block C - Roof slab except one mumty slab is complete and placing of reinforcement for the same is in progress. False ceiling, granite cladding, water proofing is in progress. 4.Land Development and parking - Drain on the western and eastern side is partly completed. Road work is in progress. LT panel room and 5 Nos. of footings are cast. Laying of hume pipes for drain, electricity cable and other services lines is in progress. |