Project Duration
Stipulated Date of Commencement December 23 2005
Actual Date of Completion March 31 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,260,953.00
Awarded for ₹ 1,391,854.80
Final Cost of Project ₹ 1,414,504.00

Project highlights

Repairing of existing road by cleaning, levelling, filling of pot holes, constructing S.W.D., catch pits, inspection chambers, precast concrete pipes, etc.

 
Contractors
M/s. Assmas Constructions Pvt. Ltd.
Consultants
M/s. Frischmann Prabhu (I) Pvt. Ltd
 