Project Duration
Stipulated Date of Commencement June 11 2014
Actual Date of Completion November 19 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,83,63,862
Awarded for ₹ 1,75,60,152.33
Final Cost of Project ₹ 11,770,994.00

Project highlights

repairs and painting of roads and kerb stones around Panaji for IFFI 2014.

 
Contractors
M/s. Abhiyant Realty, M/S. ABHIYANT REALTY, M/S. ABHIYANT REALTY
Consultants
M/s. Nitin Arolkar
 