Project Duration
Stipulated Date of Commencement May 26 2006
Actual Date of Completion February 07 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 26,014,669.00
Awarded for ₹ 32,205,615.00
Final Cost of Project ₹ 33,575,153.00

Project highlights

Main work involved widening of existing road including hot mixing, improvement of existing drainage system, signages, etc. The approximate length of the road is around 8.2 kms

 
Contractors
M/s. E. O. Thomas & Co., M/s. E. O. Thomas & Co.
Consultants
M/s. Madhav Kamat & Associates
 