Project Duration
Stipulated Date of Commencement
February 22 2014
Actual Date of Completion
May 31 2014
Status
100%
Completed
Cost (₹)
Estimated at
₹ 27,345,568.00
Awarded for
₹ 28,150,235.00
Final Cost of Project
₹ 19,489,404.00
Project highlights
Internal Roads of total approximate length of 5.7km hotmixed and widened at certain locations.
Contractors
M/s. Shaurya Construction Pvt. Ltd., M/s. Shaurya Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
Sub Works
This project involved 1 sub works. The details of the same available below
1
Hot mixing & Improvement of Internal Roads in V. P. Navelim in Navelim Constituency.
100% completed
Project Duration
Stipulated Date of Commencement
February 22 2014
Stipulated Date of Completion /
Likely Date of Completion July 04 2017
Likely Date of Completion July 04 2017
Status
100%
Completed
Cost (₹)
Estimated at
₹ 42,752,453.00
Awarded for
₹ 44,016,624.00
Final Cost of Project
₹ 44,568,658.00
Project highlights
Internal Roads of total approximate length of 3.8km hotmixed and widened at certain locations. Widening of Tolleaband road done
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
See Similar Projects
Laying of paver blocks on Promenade/Footpath along D. B. Marg in Panaji.
View ProjectConstruction of Bus Stand at Marcel, Goa – Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.
View ProjectWidening & Strengthening of the existing road from Old Goa Junction to Gaundali Bridge approach including asphalting from Old-Goa Junction to Khandola College
View Project