Project Duration
Stipulated Date of Commencement February 22 2014
Actual Date of Completion May 31 2014
Status
100%
Completed
Cost (₹)
Estimated at ₹ 27,345,568.00
Awarded for ₹ 28,150,235.00
Final Cost of Project ₹ 19,489,404.00

Project highlights

Internal Roads of total approximate length of 5.7km hotmixed and widened at certain locations.

 
Contractors
M/s. Shaurya Construction Pvt. Ltd., M/s. Shaurya Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates
 

Sub Works

This project involved 1 sub works. The details of the same available below

1

Hot mixing & Improvement of Internal Roads in V. P. Navelim in Navelim Constituency.

100% completed
 
Project Duration
Stipulated Date of Commencement February 22 2014
Stipulated Date of Completion /
Likely Date of Completion
July 04 2017
Status
100%
Completed
Cost (₹)
Estimated at ₹ 42,752,453.00
Awarded for ₹ 44,016,624.00
Final Cost of Project ₹ 44,568,658.00

Project highlights

Internal Roads of total approximate length of 3.8km hotmixed and widened at certain locations. Widening of Tolleaband road done

 
Contractors
M/s. Shaurya Construction Pvt. Ltd.
Consultants
M/s. Datta Kare Associates

See Similar Projects

Laying of paver blocks on Promenade/Footpath along D. B. Marg in Panaji.

View Project

Construction of Bus Stand at Marcel, Goa – Civil, Plumbing, Acoustic, Electrical, HVAC and Fire Fighting work.

View Project

Widening & Strengthening of the existing road from Old Goa Junction to Gaundali Bridge approach including asphalting from Old-Goa Junction to Khandola College

View Project
x