Project Duration
Stipulated Date of Commencement October 28 2014
Actual Date of Completion May 09 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 45,817,308.00
Awarded for ₹ 49,506,270.40
Final Cost of Project ₹ 49,710,987.00

Project highlights

Conversion of electrical overhead lines to underground cables.

 
Contractors
M/s. Nanu Engineers Pvt. Ltd., M/s. Nanu Engineers Pvt. Ltd.
Consultants
M/s. Nitin Arolkar
 

See Similar Projects

Look and Image Operations for the Lusofonia Games, Goa – 2014.

View Project

Renovation/Maintenance of Hospitals, CHCs, PHCs, RMDs under Directorate of Health Services in North Goa – S.H. – Supply, installation, testing and commissioning of new 12 V 17-18 AH SMF batteries, along with buy back of the old existing batteries for ARD system installed for lifts at Sub District Hospital, Ponda – Goa