Project Duration
Stipulated Date of Commencement December 15 2006
Actual Date of Completion May 19 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 18,739,000.00
Awarded for ₹ 26,300,000.00
Final Cost of Project ₹ 50,285,886.00

Project highlights

The bridge has an overall length of 150 mts. with a carriage way width of 5.5 mts. The overall length of the approaches is around 300 mts. This bridge serves as an important connectivity to the residents of Ambeshi to proceed to market area like Ponda via Ganjem during monsoon. These people had to walk around 3 kms. through hilly terrain and mining areas to reach market area like Pale thus causing inconvenience especially to school children, ladies etc.

 
Contractors
M/s. Daftary Descon Engineering Pvt. Ltd
Consultants
M/s. Kuvelkar Salkar Associates J/v M/s. Decom Consultant, M/s. Kuvelkar Salkar Associates J/v M/s. Decom Consultant
 

See Similar Projects

Resurfacing of main road from Miramar Circle to NIO Circle for IFFI 2012.

View Project

Widening of roads and relocation of structures in Fatorda Constituency- Phase I

View Project

Widening & Strengthening of the existing road from Old Goa Junction to Gaundali Bridge approach including asphalting from Old-Goa Junction to Khandola College

View Project
x