Project Duration
Stipulated Date of Commencement July 03 2015
Actual Date of Completion December 17 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 33,435,632.00
Awarded for ₹ 44,722,033.62
Final Cost of Project ₹ 38,067,779.00

Project highlights

Primary Health Centre

 
Contractors
M/s. Indage Development Construction Pvt. Ltd
Consultants
M/s. Datta Kare Associates
 