Project Duration
Stipulated Date of Commencement
August 26 2013
Actual Date of Completion
June 06 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 148,289,587.00
Awarded for
₹ 176,564,520.08
Final Cost of Project
₹ 188,075,870.00
Project highlights
Office Premises for Information Technology Department and Directorate of Information & Technology
Contractors
M/s. M. Venkata Rao Infra Projects Ltd., M/s. M. Venkata Rao Infra Projects Ltd.
Consultants
M/s. KICON Ltd., M/s. KICON Ltd.
Sub Works
This project involved 4 sub works. The details of the same available below
1
Interior works
100% completed
Project Duration
Stipulated Date of Commencement
December 19 2014
Stipulated Date of Completion /
Likely Date of Completion June 06 2016
Likely Date of Completion June 06 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 43,481,698.00
Awarded for
₹ 39,884,083.00
Final Cost of Project
₹ 36,789,320.00
Project highlights
Interior Works for IT Hub
Contractors
M/s. Srishti Enterprises
Consultants
M/s. KICONS Limited
2
Fire suppression system.
100% completed
Project Duration
Stipulated Date of Commencement
September 10 2014
Stipulated Date of Completion /
Likely Date of Completion May 25 2016
Likely Date of Completion May 25 2016
Status
100%
Completed
Cost (₹)
Estimated at
₹ 3,882,348.32
Awarded for
₹ 3,805,873.00
Final Cost of Project
₹ 3,662,345.63
Project highlights
work consists of providing fire suppression system for UPS and server room.
Contractors
M/s Douse Fire System Pvt. Ltd.,
Consultants
M/s. KICON Ltd.
3
Upgradation of RMU
100% completed
Project Duration
Stipulated Date of Commencement
August 14 2020
Stipulated Date of Completion /
Likely Date of Completion April 10 2020
Likely Date of Completion April 10 2020
Status
100%
Completed
Cost (₹)
Estimated at
₹ 2,452,762.00
Awarded for
₹ 2,214,000.00
Final Cost of Project
₹ 2,612,520.00
Project highlights
work consists of installation of 33kV SF6 gas insulated RMU
Contractors
M/s. Pristine Engineering Services
Consultants
M/s. KICON Ltd.
4
Additional works
100% completed
Project Duration
Stipulated Date of Commencement
March 08 2019
Stipulated Date of Completion /
Likely Date of Completion November 15 2019
Likely Date of Completion November 15 2019
Status
100%
Completed
Cost (₹)
Estimated at
₹ 13,817,056.68
Awarded for
₹ 15,736,138.28
Final Cost of Project
₹ 20,247,421.89
Project highlights
Structural roofing work for IT Hub
Contractors
M/S. H. Candolkar & Sons,
Consultants
M/s. KICONS Ltd.
See Similar Projects
Minor maintenance and renovation works at Goa Dental College and Hospital, Bambollim,Goa.
View ProjectFumehood, Blowers and Ducting work
View ProjectRepairs/Upgradation & Maintenance of Government Schools in the State of Goa – Civil, Plumbing & Electrical works in Dharbandora Taluka – package VIII (Rate Contract)
View Project