Project Duration
Stipulated Date of Commencement January 23 2015
Actual Date of Completion November 30 2016
Status
100%
Completed
Cost (₹)
Estimated at ₹ 14,853,393.00
Awarded for ₹ 13,328,661.00
Final Cost of Project ₹ 8,878,200.00