Project Duration
Stipulated Date of Commencement January 27 2004
Actual Date of Completion January 26 2005
Status
100%
Completed
Cost (₹)
Estimated at ₹ 47,466,000.00
Awarded for ₹ 45,103,376.00
Final Cost of Project ₹ 55,608,732.00
 
Contractors
M/s. Gannon Dunkerley & Co. Ltd., M/s. Gannon Dunkerley & Co. Ltd.
Consultants
M/s. Madhav Kamat & Associates
 

Sub Works

This project involved 5 sub works. The details of the same available below

1

Interior Works

100% completed
 
Project Duration
Stipulated Date of Commencement December 30 2005
Stipulated Date of Completion /
Likely Date of Completion
May 13 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,998,478.00
Awarded for ₹ 2,123,561.34
 
Contractors
M/s. Deshpande Constructions
Consultants
M/s. Madhav Kamat & Associates
2

Design, manufacture, supply, installation, testing, commissioning and maintenance of elevators

100% completed
 
Project Duration
Stipulated Date of Commencement December 30 2005
Stipulated Date of Completion /
Likely Date of Completion
September 06 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,970,000.00
Awarded for ₹ 1,793,000.00
 
Contractors
M/s. Schindler (I) Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates
3

Supply, installation, testing and commissioning of transformer yard and diesel generating set.

100% completed
 
Project Duration
Stipulated Date of Commencement June 15 2006
Stipulated Date of Completion /
Likely Date of Completion
September 14 2006
Status
100%
Completed
Cost (₹)
Estimated at ₹ 2,919,050.00
Awarded for ₹ 3,119,950.00
 
Contractors
M/s. G. V. Electricals
Consultants
M/s. Madhav Kamat & Associates
4

Construction of Sewage Treatment Plant and Elevated tank platform.

100% completed
 
Project Duration
Stipulated Date of Commencement July 23 2006
Stipulated Date of Completion /
Likely Date of Completion
April 15 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,144,443.00
Awarded for ₹ 1,210,535.00
 
Contractors
M/s. Chowgule Industries (I) Ltd.
Consultants
M/s. Madhav Kamat & Associates
5

Supply, installation, testing and commissioning of Air Conditioners and ventilation system

100% completed
 
Project Duration
Stipulated Date of Commencement September 10 2006
Stipulated Date of Completion /
Likely Date of Completion
May 20 2007
Status
100%
Completed
Cost (₹)
Estimated at ₹ 1,247,890.00
Awarded for ₹ 1,654,105.00
 
Contractors
M/s. Vigneshwar Air Conditioning Pvt. Ltd.
Consultants
M/s. Madhav Kamat & Associates

See Similar Projects

Medical gases & vacuum system works

View Project

Internal Electrical works

View Project

Upgradation of Morgue situated at T. B. Sanatorium, Monte Hill, Marga

View Project
x