Project Duration
Stipulated Date of Commencement
October 31 2009
Actual Date of Completion
September 25 2012
Status
100%
Completed
Cost (₹)
Estimated at
₹ 49,990,185.00
Awarded for
₹ 51,999,999.00
Final Cost of Project
₹ 56,712,649.00
Project highlights
Total built up area – 3244 m2. Facilites include Wards for male and female with toilets and nurse station, pharmacy, casualty, consulting rooms, ICU, OT, Paid wards, Office, canteen, doctors rest rooms. Hospital is provided with lift, ramp, medical gases line, Air conditioning, fire fighting and fire alarm system, medical and non medical furniture, solar water heating system and generator backup
Contractors
Acron Developers, Acron Developers
Consultants
Datta Kare Associates, Datta Kare Associates
See Similar Projects
Supply Installation Testing & Commissioning of shadowless lamps, electro / mech hydraulic tables, etc. for Operation Theatre.
View ProjectSteel Operation Theatre.
View ProjectCivil, Plumbing, Electrical, Lift & Fire – Fighting works- Balance works
View Project